133126Install one flat washer and pulley screwTorque the screw to 120-144 inIbs(14-16 Nm)13427Install nut onto pulley screwTorque
of the pulley is aligned with the rope guideUSin.ga C-clamp and wood blocks, clamp the pulley in this position34Inspect the
starter ropeIf replacement is needed, cut new rope to length of 96112 in (245 cm)Fuse ends of rope to length of V2 in(12
mm)3735Insert the rope through the starter handle bracket, .rope guide into the starter pulley3836Tie knot in end of starter
rope as illustrated3937 Insert the knot in the rope cavity of the starter pulley38Tie knot in the rope approximately 12 in(30,5
cm) from the handle end39Carefully loosen the C-clamp and slowly allow the rope to recoil until the knot contacts the starter